Project:
|
Winstone Aggregates - Relocation
and Installation of Sand Grading/Sorting Plant |
Duration:
|
3 months |
Project Description:
This project had a critical time frame, as there
would be no new product
manufactured during the relocation period.
Therefore the client was required to stockpile product and only
had these
reserves to work with during the relocation.
We worked very closely with our client in the months leading up
to the project
start. This included detailing, scheduling and planning
tasks for each day as
well as site safe management for the project
duration.
Work carried out included: