Project:
|
Fulton Hogan Ltd - Hampton Downs
Land Fill
Leachate Collection System |
Duration:
|
12 months |
Project Description:
Because both Auckland and Hamilton are close
in proximity to this area,
Hampton Downs was chosen to site New Zealand’s
largest landfill operation.
With the enormous volumes of refuse being delivered, this site covers
a very
large area. After rainfall has filtered down through the layers
of refuse it is
collected in its liquid form known as leachate.
This leachate is pumped from a pumping station site located at the
bottom
of the valley up to holding tanks where tankers collect the
leachate and
transport it to a treatment facility at an off site location.
Each remote pumping station and the central base station are in constant
communication with each other by using a telemetry system.
This project was a design and build type contract where Hennessy Group
designed the cabinets, the control systems inside the cabinets, and
performed
all field installation and commissioning
Due to the looming closure of Auckland landfills the timeline was
very tight
on this project as this new landfill had to be up and running
before these other
landfills finished operating.
Work carried out included:
 |
Detailed logistics and pre-planning. |
 |
Design IP65 powder coated electrical & telemetry
cabinets. |
 |
Design gear tray layouts and assemble all components,
trunking
and din rail to the formica backplanes. |
 |
Terminate all wiring
including individual core labels. |
 |
Deliver to site and
install. |
 |
Install multiple underground
cabling systems between
cabinets and field devices. |
| |
|